News  

13 March 2019

The polypropylene unit at ZapSibNeftekhim, a deep hydrocarbon conversion plant under construction, is 99.8% complete. Construction and installation works on the process unit are over, and commissioning is underway. In particular, systems are undergoing functional testing and safety systems are being checked for proper performance.

13 March 2019

The polypropylene unit at ZapSibNeftekhim, a deep hydrocarbon conversion plant under construction, is 99.8% complete. Construction and installation works on the process unit are over, and commissioning is underway. In particular, systems are undergoing functional testing and safety systems are being checked for proper performance.

12 February 2019

A 13 ktpa capacity ramp-up will increase total capacity to 48 ktpa and enable the Company to meet the strong demand for Nd-BR in the target markets of the CIS and Europe.

Photo

More

Video

More